Specify the filtration duty and the complete bag’s wet-load rating together. Four loops or strong fabric alone do not establish that a filled bag can be lifted safely.
Review my bag requirementsSend the sludge, filled mass, required volume and a photo of the lifting equipment. Include the tender’s test and marking requirements.
Actual enquiry · 19 March 2026
An industrial recycler requested 4 m³ bags for sludge and concrete slurry, SWL 4–6 t, safety factor at least 5:1, four heavy-duty lifting loops and 80–150 μm filtration zones. These are the buyer’s requested conditions, not a product rating or a certificate held by XILINK. Manufacture and suitability must be checked against the complete design and tests.
Start with the wet load at the moment of lifting.
Nominal volume does not establish the weight. Determine the actual filled volume and measured bulk density at the intended lifting stage. Slurry before drainage and cake after drainage can have different loads and behaviour.
Illustration only: 1.5 t/m³ is an assumed density. It gives 6 t of contents before adding the bag or other items carried by the lifting equipment. The required bag rating and the handling system must be checked for the actual conditions. A 4 m³ description alone does not approve this load.
A safety factor is part of a defined design and test basis. It does not multiply the permitted working load. Agree the proposed SWL, use category and test protocol with the responsible manufacturer before purchase.
Dewatering and lifting need evidence for the same bag
Whole-bag mechanical qualification
Construction identity
The report identifies bag dimensions, fabric, seams, base, lifting loops and attachments. A tensile strip or a loop tested alone cannot establish the rated capacity of the assembled bag.
Test and use basis
Confirm the applicable standard and edition, test loads and cycles, conditions, results and approved use category. The manufacturer must assess whether the actual contents and handling arrangement fall within that scope.
Representative sludge trial
Retention and drainage
Test the actual slurry and any conditioning with the proposed filter zones. State the opening-size method, solids retention, drainage over time and resulting cake. A micron range or fabric mass alone does not predict the whole process.
Filtrate and chemistry
Record relevant chemistry, temperature and filtrate acceptance requirements. Concrete slurry, industrial sludge and hazardous contents cannot be treated as one generic fill. Clear-looking filtrate is not evidence of permitted discharge.
Send the sludge, filled mass, required volume and a photo of the lifting equipment. Include the tender’s test and marking requirements.
Review my bag requirementsFour loops do not approve a loader or hook.
Handling connection
Provide the proposed machine, lifting attachment and connection geometry for the bag maker and responsible lifting specialist to review. The machine-and-attachment combination needs sufficient capacity for the actual filled load. Do not infer approval for a wheel-loader bucket from a four-loop description.
Use and condition
Follow the manufacturer-approved lifting method and use all intended lifting points. Confirm inspection, storage and reuse limits for the exact bag. Chemical damage, abrasion, UV exposure and damaged stitching can change its condition; a new-bag test report is not permission to reuse a damaged bag.
ISO 21898:2024 covers specified construction, type-testing and marking for non-dangerous solid/paste FIBCs. Its title is not a certificate for this requested dewatering design. Ask which standard and report actually cover the proposed product, content and use.
Match the order to the accepted evidence.
| Order line | Confirm before supply |
|---|---|
| Accepted construction | Drawing revision, fabric and seams, loops and base; complete-bag test identity, approved SWL and use category; matching bag marking. |
| Dewatering and handling | Actual slurry trial, filtrate basis, filling limits and the approved lifting arrangement. Keep untested values explicit. |
| Supply and packing | Quantity, destination, documents and packing; factory feasibility and current offer for the requested construction. XILINK coordinates the clarification and comparison. |
Review my bag requirements
Send the sludge, filled mass, required volume and a photo of the lifting equipment. Include the tender’s test and marking requirements.
We review the requirements and identify the information the factory needs before preparing a scoped quotation. Unknown details can be discussed.
The supply and transport scope is checked for your destination, including the local installation boundary.